Strip-out and demolition of a live rooftop plant room, including breaking out concrete plinths, delivered in two phases.

R.E.B Group has been appointed to undertake strip-out and demolition works to a live rooftop plant room on Weymouth Street, London.

The works include the controlled strip-out and demolition of existing plant room elements, including breaking out concrete plinths and associated structures.

Project delivery

Due to the project taking place within a live rooftop environment, the works will be carefully planned and coordinated to maintain safe access and minimise disruption throughout the programme.

The project is planned to be delivered in two phases over approximately 5–6 weeks, with a resource allowance of 125 man-days. Access for deliveries will be via Wimpole Mews, with the programme start subject to completion of the required scaffolding.

Pre-construction planning includes a dedicated pre-start meeting, followed by RFIs and confirmation of the required asbestos survey for the site.

Project highlights

  • Strip-out and demolition of a live rooftop plant room
  • Breaking out of existing plinths and structural elements
  • Two-phase programme over 5–6 weeks
  • 125 man-day resource allowance
  • Controlled delivery access via Wimpole Mews
  • Pre-construction coordination and RFI process
  • Works programmed around scaffolding completion