Natural History Museum, Royal Borough of Kensington and Chelsea
The scope included the removal of existing roof louvre panels, roof snagging works involving the removal of redundant bolts, and the removal of a plasterboard ceiling within a ground-floor rear room.
Project overview
R.E.B Group Ltd was appointed by Bloom to undertake specialist strip-out and removal works at the Natural History Museum, Cromwell Road, South Kensington, London, SW7 5BD.
The project involved a combination of external roof works and internal removal works, requiring careful planning and coordination within a busy, high-profile museum environment.
The scope included the removal of existing roof louvre panels, roof snagging works involving the removal of redundant bolts, and the removal of a plasterboard ceiling within a ground-floor rear room.
Working to a one-week programme, our team followed a detailed method statement and risk assessment to ensure the works were carried out safely, with consideration for the building, other contractors and members of the public.
The challenge
Working within the Natural History Museum presented several important considerations. The roof works required controlled access at height, careful handling of removed metal panels and coordination with the main contractor's access and lifting arrangements.
The work also needed to be undertaken without damaging the existing roof areas that were to remain or interfering with services and building systems.
The key challenges included:
- Working at roof level: Accessing the designated roof area safely using the agreed scaffold access and walkway.
- Louvre panel removal: Removing existing metal louvre panels in manageable sections while avoiding damage to surrounding roof surfaces.
- Roof snagging: Removing redundant bolts and fixings, selecting suitable cutting methods and controlling the risks associated with hot works.
- Internal ceiling removal: Taking down the plasterboard ceiling in the rear ground-floor room while avoiding concealed services and controlling falling debris.
- Public and contractor safety: Managing the movement of materials and waste through shared areas, with suitable precautions to protect other site users.
- Building protection: Working around existing services and ensuring that the live fire alarm system and other building systems were not disturbed.
Our approach
R.E.B Group Ltd planned the works around the specific requirements of each work area, using suitable tools, access arrangements and handling methods.
1. Roof strip-out and louvre removal
The first element of the roof package involved removing the existing louvre panels.
The RAMS specified that the panels were to be removed in sections, taking advantage of their existing installation arrangement. Where possible, fixings were to be released using an impact drill with the correct bits or an adjustable spanner. Where fixings could not be removed conventionally, a reciprocating saw with metal-cutting blades could be used.
Particular care was taken to avoid placing sharp metal objects directly onto the existing roof surface, helping to prevent unnecessary damage.
Once released, the panels were to be moved across the roof in manageable sections, transferred over the scaffold and lowered to ground level using the main contractor's goods-only one-tonne hoist.
Where sections were too large or heavy for one operative, a two-person lift was specified.
2. Roof snagging works
The roof package also included snagging works involving the removal of redundant bolts.
Our planned approach prioritised the use of a reciprocating saw with metal-cutting blades. Where this was not suitable, a four-inch grinder could be used, subject to the correct blade, guard and equipment checks.
The RAMS also identified the need for a hot works permit before any grinding took place, with a suitable fire extinguisher available and a one-hour fire watch following completion of hot works.
These controls helped ensure that the snagging activities were properly managed and that risks associated with cutting metal were considered before work commenced.
3. Ground-floor ceiling removal
The revised method statement also included removal of the plasterboard ceiling in the rear ground-floor room.
The ceiling was to be taken down by hand, starting in an agreed area and working from a suitable delta deck. A crowbar would be used to create an initial opening, allowing the plasterboard to be carefully pulled down.
Where fixings were accessible, these would be removed using the appropriate tools. Cutting was only to be considered where the location of the material was clearly visible, reducing the risk of accidentally damaging concealed services.
The delta deck was required to be erected by a trained and competent person, inspected and signed off before use.
The removed plasterboard was to be placed in a safe, agreed storage area before being transferred for disposal.
4. Waste management and housekeeping
Waste handling was an important part of the project, particularly given the museum's public setting and the restricted delivery and collection arrangements.
The RAMS specified that deliveries and waste collections on Exhibition Road were restricted to the 6:30am–9:00am window.
Waste was to be stored neatly in an agreed location, kept at manageable weights and removed using the designated waste arrangements. Two operatives were required to be present during vehicle loading to help manage the risks to the public and the workforce.
Good housekeeping was maintained as a key control, with waste areas kept tidy and materials prevented from creating trip hazards or risks to other site users.
Site management, health and safety
The project was supported by a detailed risk assessment and method statement, covering work at height, manual handling, cutting operations, dust, noise, electrical tools, fire safety and public protection.
Key control measures included:
- Site induction and briefing of all operatives on the agreed RAMS before work commenced.
- Use of the designated scaffold access, roof walkway and existing handrails.
- Restricting roof activities to the designated working area within the handrails.
- Checking that services had been isolated or made safe by the relevant contractor before work began.
- Inspection of tools and equipment before use, with defective equipment removed from service.
- Use of suitable PPE, including hard hats, safety footwear, high-visibility clothing, gloves and eye protection.
- FFP3 respiratory protection where required for dusty activities.
- Dust control through suitable extraction, vacuuming and wet cleaning rather than dry sweeping.
- Appropriate permits, fire extinguishers and fire-watch arrangements if hot works were required.
- Barriers or a designated watcher where necessary to protect other contractors and third parties.
The RAMS also required daily work records and ongoing checks by the site supervision and management team.
Outcome
The planned package brought together roof strip-out, metalwork snagging and internal ceiling removal within a single coordinated programme.
The approach set out in the RAMS provided a clear sequence for removing the roof louvres, managing redundant fixings and taking down the plasterboard ceiling, while controlling access, waste handling and the risks associated with working in an occupied public building.
The project demonstrates R.E.B Group Ltd's ability to undertake specialist removal and strip-out activities in a complex building environment, where careful coordination, protection of existing structures and public safety are essential.
Summary
The Natural History Museum project showcases R.E.B Group Ltd's experience in delivering controlled strip-out and removal works within a prominent London building.
Working for Bloom, the package included roof louvre removal, roof snagging and ground-floor plasterboard ceiling removal. Each activity required a considered approach to access, material handling, service protection and waste management.
Through detailed planning, suitable equipment and clear health and safety controls, R.E.B Group Ltd established a practical method for delivering the works within the museum environment.
The project further demonstrates our ability to adapt our approach to different work areas and deliver specialist building works in locations where the protection of the public, existing building fabric and other contractors is paramount.